Bartow County

  • Old Alabama Road Widening: The project is about 43% complete. Current Completion Date: End of 2024.
  • Cassville-White Road Roundabout Construction: The project is approximately 62% complete. Crews continue to build the roundabouts as well as new interstate ramps. Current Completion Date: Spring 2024.
  • Highway 41 Bridge Construction over State Route 293 and CSX railroad in Emerson: Work is just beginning. Current Completion Date: End of 2025.

Gordon and Bartow County

  • Resurfacing I-75 from US 411 to Dews Pond Road overpass: Approximately 9% complete. Current Completion Date: Early 2024.

Polk County

  • Bridge construction on SR 101 over Euharlee Creek Tributary: 27% complete. Preparing to install main water pipe. Current Completion Date: Summer 2024.

Chattooga County

  • Bridge construction on SR 48 over Raccoon Creek: 34% complete. Current Completion Date: Summer 2024.

Floyd County

  • Bridge construction on SR 293 over Dykes Creek: 8% complete. Current Completion Date: Late 2025.
  • Resurfacing SR 20 from SR 100 to SR 1: 4% complete. Current Completion Date: Late 2023.